Issue 52: Extended Electrical-Service Equipment Lead Times
Extended Electrical-Service Equipment Lead Times By Ashley McDuffee, PE, LEED AP BD+C, Project Engineer At numerous projects over the past year, GTG has observed and monitored extraordinarily long lead times for electrical-service equipment, such as switchgear, metering materials, and transformers, which have significantly impacted critical-path schedules. Switchgear lead times of 50 to 80 weeks have […]